East Side Access

East Side Access - 07-26-19

ESA Progress Photos

By | East Side Access

QUEENS WORK 1. Placing and leveling stone for the base of an approach structure in Harold Interlocking. 2. A crane placing pre-fab modules for a traction power substation in Queens. 3. Demolition of old catenary spans in Harold Interlocking in preparation for installing new ones. 4. Installing new catenary spans…

Read More
East Side Access 07-12-19

ESA Progress Photos

By | East Side Access

MANHATTAN WORK 1. Installation of ceiling frames on the lower level platform in the future LIRR Terminal beneath Grand Central. 2. Installation of stone tiles over an archway in the future LIRR Concourse. 3. Installing supports for stainless steel plates between the escalator and the wall at escalator Wellway Two….

Read More
East Side Access - 06-28-19

ESA Progress Photos

By | East Side Access

MANHATTAN WORK 1. Track work in the Manhattan tunnels leading into the new LIRR Terminal beneath Grand Central. 2. Pouring concrete for a newly graded sidewalk at the northern end of the LIRR concourse. QUEENS WORK 3. Backfilling soil for a power substation in the future Mid-Day Storage Yard. 4….

Read More