Carle Place Station

Carle Place Schools 09-18-19

LIRR Expansion Project Team Discusses Successful Cherry Lane Bridge Installation and Carle Place Station Improvements with Carle Place School District Superintendent

By | Carle Place Station, LIRR Expansion Project

The LIRR Expansion Project team continues its robust coordination efforts with school districts throughout the project corridor. The team recently met with the Superintendent of Carle Place School District, Dr. Christine Finn, and the Director of Transportation, Kevin Coffey, to discuss ongoing construction work in Carle Place, including the successful…

Read More
Councilwoman Vivianna Russell - 07-29-19

Town of North Hempstead Councilwoman Viviana Russell Records Interview Segment at Community Information Center

By | Carle Place Station, Cherry Lane Bridge, LIRR Expansion Project, Urban Avenue Grade Crossing

On July 15th, Town of North Hempstead Councilwoman Viviana Russell recorded an interview about the LIRR Expansion Project at the Community Information Center in Mineola. Councilwoman Russell highlighted the project’s benefits to Carle Place and New Cassel, including ongoing station enhancements at Carle Place and the elimination of the Urban…

Read More
Carle Place 07-03-19

Eastbound Platform Construction Progresses at Carle Place Station

By | Carle Place Station, Project Update

Improvements to Carle Place LIRR station continue including platform replacement to accommodate 12-car trains, a new pedestrian bridge with ADA-elevators, and an improved customer drop-off and pickup area. Concrete platforms have been placed to support the new eastbound platforms on the south side of Carle Place Station. Demolition of the…

Read More

Significant Progress at Cherry Lane Bridge Replacement Project

By | Carle Place Station, Cherry Lane Bridge, LIRR Expansion Project

Construction of the bridge continues at the Cherry Lane Bridge Replacement project, with Cherry Lane closed to traffic. Once construction is completed, safety inspections will be conducted, followed by the roll-in and installation of the new three-track bridge, which is scheduled for the first weekend of June. Cherry Lane Bridge…

Read More
Carle Place Fire Department - 04-11-19

LIRR Expansion Project Team Discusses Cherry Lane Bridge Replacement with Nassau County Legislator’s Office and Local Officials and Associations

By | Carle Place Station, Carle Place Substation, Cherry Lane Bridge, Glen Cove Bridge, LIRR Expansion Project, Meadowbrook Parkway Bridge

On April 11th, the Carle Place Fire Department, Carle Place Civic Association, Nassau County Legislator Laura Schaefer’s office, and Town of North Hempstead Councilwoman Viviana Russell invited the LIRR Expansion Project team to discuss the ongoing construction work and traffic detours at Cherry Lane Bridge.  Coordination with local emergency service…

Read More