East Side Access Progress Photos

QUEENS WORK

  1. Removing old cables from a trough in preparation of the construction of a new approach structure.

East Side Access 04-29-19

  1. Installing bridge roof panels on the personnel bridge for the Mid-Day Storage Yard.

East Side Access 04-29-19

  1. Installing new hardware on catenary poles as part of ongoing improvements in Harold Interlocking.

East Side Access 04-29-19

  1. Fusing pipes for an underdrain that will service the Mid-Day Storage Yard.

East Side Access 04-29-19

  1. Backfilling a sewer roof for the future Mid-Day storage yard.

East Side Access 04-29-19

MANHATTAN WORK

  1. Rebar reinforcements for the stairs at the 47th Street exit from the new LIRR Concourse.

East Side Access 04-29-19

For more information and images, please visit the East Side Access project page on AModernLI.com – //www.amodernli.com/project/east-side-access/.