East Side Access Progress Photos

MANHATTAN WORK

1. Concrete pour to set track in the upper level of the east cavern.

East Side Access 05-29-19

2. Demolition of steel at the Biltmore Room connection.

East Side Access 05-29-19

3. Ironworkers welding a column in the back of house area of the future LIRR passenger concourse.

East Side Access 05-29-19

4. Identifying power feed and control wires in a recently energized power substation.

East Side Access 05-29-19

QUEENS WORK

5. Ballast support for newly installed track for the Mid-day storage yard.

East Side Access 05-29-19

6. Amtrak workers transferring catenary wires between old and new poles in Harold Interlocking.

East Side Access 05-29-19

7. Building a turnout for the Mid-day storage yard.

East Side Access 05-29-19

8.Soldier pile installation that will support a new approach structure east of the 39th Street bridge.

East Side Access 05-29-19

9. Pouring concrete to support a soldier pile in Harold Interlocking.

East Side Access 05-29-19

For more information and images, please visit the East Side Access project page on AModernLI.com – //www.amodernli.com/project/east-side-access/.