QUEENS WORK

1. Placing and leveling stone for the base of an approach structure in Harold Interlocking.

East Side Access - 07-26-19

2. A crane placing pre-fab modules for a traction power substation in Queens.

East Side Access - 07-26-19

3. Demolition of old catenary spans in Harold Interlocking in preparation for installing new ones.

East Side Access - 07-26-19

4. Installing new catenary spans and insulators in Harold Interlocking.

East Side Access - 07-26-19

5. Excavating for the final approach structure in Harold Interlocking west of the 39th St Bridge.

East Side Access - 07-26-19

6. Installing a ballast retaining wall east of the Thomson Ave Bridge in the future Mid-Day Storage Yard.

East Side Access - 07-26-19

7. A newly constructed CIL Hut ready to ship to Queens for installation in the future Mid-Day Storage Yard.

East Side Access - 07-26-19

For more information and photos of work at East Side Access, please visit the East Side Access project page on AModernLI.com – http://www.amodernli.com/project/east-side-access/.