Rebar Delivered for Concrete Pour for Foundation at Westbury North Parking Structure

Westbury North Parking Structure - 07-31-19

Excavation continues at the Westbury North Parking Structure. The installation of support of excavation (SOE) continues, and rebar continues to be delivered in advance of the concrete pour for the structure’s foundation.

Westbury North Parking Structure - 07-31-19

Up to 100 tons of rebar will be delivered for the foundation and 15,000 tons of dirt is being hauled away by truck.

Westbury North Parking Structure - 07-31-19

Foundation work is scheduled to be completed in December of this year, with completion of the entire structure scheduled for spring 2021.

The Westbury North Parking Structure is a new four-level, 683-space parking structure currently under construction near the Westbury Station north of the LIRR tracks and occupying the current surface parking lot south of Scally Place. The new garage will retain 106 surface parking spaces and will add a net increase of 481 parking spaces.

For more information and photos of ongoing construction, please visit the Westbury North Parking Structure project page on AModernLI.com – //www.amodernli.com/project/westbury-north-parking-structure/.