Accabonac Road - 11-18-19
Bridges

Accabonac Road / North Main Street Bridge Replacements (Completed 11/2019)

East Hampton

Accabonac Road and North Main Street bridges have been replaced to reduce truck strikes and improve infrastructure.

Baldwin Station 11-08-18
Completed

Baldwin Station Enhancement (Completed 06/2019)

Baldwin

Baldwin Station has received modernized station enhancements and upgrades.

Bayside Station
Completed

Bayside Station Enhancement (Completed 03/2019)

Bayside

Bayside Station has received modernized station enhancements and upgrades.

Bellmore Station Enhancement (Completed 06/2019)
Completed

Bellmore Station Enhancement (Completed 06/2019)

Bellmore

Bellmore Station has received modernized station enhancements and upgrades.

Bellmore Substation 2-13-18
Infrastructure Improvements

Bellmore Substation Replacement

Bellmore

The Bellmore substation will be replaced to provide more reliable power to LIRR trains.

Brentwood Station 11-08-18
Completed

Brentwood Station Enhancement (Completed 06/2019)

Brentwood

Brentwood Station has received modernized station enhancements and upgrades.

Buckram Road Bridge Replacement 02-20-20
Bridges

Buckram Road Bridge Replacement (Completed 10/2019)

Town of Oyster Bay
Hamlet of Locust Valley

Buckram Road Bridge has been replaced to reduce truck strikes and improve infrastructure.

Carle Place Station Enhancement (rendering)
Station

Carle Place Station Enhancement

Town of North Hempstead
Hamlet of Carle Place

Carle Place Station is receiving modernized station enhancements and upgrades.

Carle Place Substation
Infrastructure Improvements

Carle Place Substation Replacement

Carle Place

The Carle Place substation will be replaced to accommodate the additional third track on the Main Line.

Cherry Lane Bridge 06-03-19
Bridges

Cherry Lane Bridge Replacement (Completed 06/2019)

Town of North Hempstead
Hamlet of Carle Place

Cherry Lane Bridge has been replaced to reduce truck strikes and improve infrastructure.

Cherry Valley Road Bridge Prior to Construction
Bridges

Cherry Valley Road Bridge Replacement

Garden City

Cherry Valley Road Bridge will be replaced to reduce truck strikes and improve infrastructure.

Covert Avenue Grade Crossing Elimination Offical Opening of Underpass - 10-17-19
Completed

Covert Avenue Grade Crossing Elimination (Completed 10/2019)

New Hyde Park

Covert Avenue Grade Crossing Elimination – Completed October 2019

Deer Park Dahlias (2018) © William Low, LIRR Deer Park Station
Completed

Deer Park Station Enhancement (Completed 04/2019)

Baywood

Deer Park has received modernized station enhancements and upgrades.

East End Gateway Entrance 12-31-20
System Expansion

East End Gateway and LIRR Concourse

Manhattan

The 33rd Street Corridor will be widened and redesigned and accessible from a new entrance pavilion.

Completed

East Hampton Station Enhancement (Completed 04/2019)

East Hampton

East Hampton has received modernized station enhancements and upgrades

East Side Access Removed 08-03-2018
System Expansion

East Side Access

Queens, Manhattan

A transformative project connecting LIRR to Grand Central Terminal.

Station

Elmont Station

Elmont

The new Elmont LIRR Station, the first new full-time LIRR station in nearly 50 years, is part of the $1.26 billion Belmont Park Redevelopment Project.

Farmingdale Station 11-08-18
Completed

Farmingdale Station Enhancement (Completed 04/2019)

Farmingdale

Farmingdale Station has received modernized station enhancements and upgrades.

Parking

Floral Park Parking Re-Surfacing at Creedmoor Spur

Floral Park

This popular Village parking area will be repaved and restriped.

Floral Park Station - 03-07-19
Station

Floral Park Station Enhancement

Floral Park

Floral Park Station is receiving modernized station enhancements and upgrades.

Infrastructure Improvements

Floral Park Substation Modifications

Floral Park

The Floral Park substation will be modified to accommodate the additional third track on the Main Line.

Flushing Main Street Bridge
Bridges

Flushing Main Street Bridge Rehabilitation (Completed 11/2019)

Flushing

Flushing Main Street Bridge has been rehabilitated.

Flushing Main Street Station 8-31-2018
Station

Flushing Main Street Station Enhancement (Completed 08/2018)

Flushing, Queens

Flushing Main Street Station has received modernized station enhancements and upgrades.

Glen Cove Rd Bridge 09-22-20
Bridges

Glen Cove Road Bridge Replacement (Completed 06/2020)

Town of North Hempstead
Hamlet of Carle Place

Glen Cove Road Bridge is being replaced to improve infrastructure and accommodate a new third track on the mainline.

Completed

Great Neck Station Enhancement (Completed 04/2019)

Great Neck

Great Neck Station has received modernized station enhancements and upgrades.

Hempstead Station - 03-12-19
Completed

Hempstead Station Enhancement (Completed 07/2019)

Hempstead Station

Hempstead Station has received modernized station enhancements and upgrades.

Parking

Hicksville Parking/Downtown Revitalization Initiative

Hicksville

The MTA is working with the Town to fulfill their vision of a walkable community that enlivens the train station area.

Hicksville Station Improvements Project (Completed 08/2018)
Completed

Hicksville Station Improvements Project (Completed 08/2018)

Hicksville

Hicksville Station has been completely renovated with modernized station enhancements and upgrades.

Infrastructure Improvements

Hicksville Substation Replacement

Hicksville

The Hicksville substation will be replaced to accommodate the additional third track on the Main Line.

Project Rendering
System Expansion

Jamaica Capacity Improvements

Jamaica, Queens

A comprehensive reconfiguration of Jamaica Station is currently underway to improve capacity and reliability.

Laurelton Station - 03-12-19
Completed

Laurelton Station Enhancement (Completed 12/2019)

Laurelton

Laurelton Station has been improved and modernized.

Linden Avenue Pedestrian Underpass 04-29-20
Completed

Linden Avenue Pedestrian Underpass (Completed 04/2020)

Village of Floral Park

The pedestrian underpass at Linden Avenue in Floral Park is being replaced to accommodate the new third track on the Main Line.

Completed

LIRR Double Track Project Farmingdale to Ronkonkoma (Completed 09/2018)

Farmingdale to Ronkonkoma

The Double Track Project introduces 13 miles of a new second track between Farmingdale and Ronkonkoma.

LIRR Expansion Project Floral Park to Hicksville
System Expansion

LIRR Expansion Project Floral Park to Hicksville

Floral Park to Hicksville

The LIRR Expansion Project will introduce 9.8 miles of a new third track, close dangerous grade crossings and upgrade stations along this heavily traversed corridor.

Locust Manor Station Enhancement - 03-12-19
Completed

Locust Manor Station Enhancement (Completed 05/2019)

Locust Manor

Locust Manor Station has been modernized and upgraded.

Lynbrook Station Enhancement (rendering)
Completed

Lynbrook Station Enhancement (Completed 10/2020)

Lynbrook

The Lynbrook Station infrastructure is being renewed and its amenities are being upgraded.

Lynbrook Viaduct - 10-24-19
Bridges

Lynbrook Viaduct Rehabilitation

Lynbrook

The Lynbrook Viaduct is being rehabilitated and repaired, including improvements to the existing drainage system.

Grade Crossings

Main Street Grade Crossing Elimination

Mineola

The elimination of the Main Street grade crossing will alleviate train and vehicular traffic and enhance safety.

Bridges

Meadowbrook Parkway Bridge Modification (Completed 9/2020)

Town of North Hempstead
Hamlet of Carle Place

Meadowbrook Parkway Bridge is being modified to improve infrastructure and to accommodate a third track on the Main Line.

Meadowbrook Substation Replacement 10-12-18
Completed

Meadowbrook Substation Replacement (Completed 06/2020)

Freeport

The Meadowbrook substation will be replaced to provide more reliable power to LIRR trains.

Station

Merillon Avenue Station Enhancement

Garden City

Merillon Station will receive modernized station enhancements and upgrades.

Infrastructure Improvements

Merillon Avenue Substation Replacement

Garden City

The Mineola substation, located at the southwest corner of Main Street and Front Street in Mineola, will be replaced as part of the LIRR Expansion Project.

Merrick Station Enhancement
Completed

Merrick Station Enhancement (Completed 01/2019)

Merrick

Merrick Station has received modernized station enhancements and upgrades.

Mets-Willets Point Station Pre-Construction
Station

Mets-Willets Point Station

Flushing, Queens

The seasonal Mets-Willets Point Station will receive modernized station enhancements and upgrades.

Completed

Mid-Suffolk Train Storage Yard (Completed 11/2020)

Ronkonkoma

An expanded train storage yard and a new employee facility are being built to meet the anticipated increase in AM and PM peak ridership once East Side Access opens in 2022.

Parking

Mineola 2nd Street Parking

Mineola

New parking is planned at the Mineola Station Second Street Parking Lot.

Mineola Harrison Avenue Parking Structure 10-25-19
Parking

Mineola Harrison Avenue Parking Structure

Mineola

A new parking garage is being constructed at Mineola Station west of Mineola Boulevard between Harrison Avenue and First Street.

Parking

Mineola Main Street Parking and Drop-Off

Mineola

New surface parking and a kiss-and-ride will be constructed at Mineola Station.

Station

Mineola Station Enhancement

Mineola

Mineola Station will receive modernized station enhancements and upgrades.

Mineola Substation Prior to Construction
Infrastructure Improvements

Mineola Substation Replacement

Mineola

The Mineola substation, located at the southwest corner of Main Street and Front Street in Mineola, will be replaced as part of the LIRR Expansion Project from Floral Park to Hicksville.

Completed

Morris Park Diesel Locomotive Shop (Completed 11/2020)

Queens

Morris Park Diesel Locomotive Shop is receiving upgrades to maximize efficiency.

Moynihan Train Hall (rendering)
Completed

Moynihan Train Hall (Completed 12/2020)

Manhattan

The new Moynihan Train Hall will alleviate overcrowding at Penn Station and improve the customer experience for LIRR passengers.

Murray Hill Station prior to enhancements
Completed

Murray Hill Station – New Elevators (Completed 04/2020)

Queens

Murray Hill Station is receiving modernized station enhancements and upgrades.

Murray Hill Substation – 01-29-19
Infrastructure Improvements

Murray Hill Substation Replacement

Queens

The Murray Hill substation will be replaced to provide more reliable power to LIRR trains.

Nassau Bridge 02-14-20
Bridges

Nassau Boulevard Bridge Replacement (Completed 10/2019)

Garden City

Nassau Boulevard Bridge Replacement – Completed October 2019

Infrastructure Improvements

New Cassel Substation Replacement

New Cassel

The New Cassel substation will be replaced to accommodate the additional third track on the Main Line.

Completed

New Hyde Park Road Grade Crossing Elimination (Completed 08/2020)

New Hyde Park

The New Hyde Park Road grade crossing is being eliminated to alleviate train and vehicular traffic and improve safety.

Parking

New Hyde Park Road Surface Lot

New Hyde Park

A new surface lot and a kiss-and-ride will be constructed at New Hyde Park Station between Plaza Avenue and Second Avenue.

Station

New Hyde Park Station Enhancement

New Hyde Park

New Hyde Park Station will receive modernized station enhancements and upgrades.

New Hyde Park Substation Replacement
Infrastructure Improvements

New Hyde Park Substation Replacement

New Hyde Park

The New Hyde Park substation will be replaced to accommodate the additional third track on the Main Line.

New M9 Rail Cars
System Expansion

New M9 Rail Cars

Long Island

The next generation of commuter rail cars is coming to the Long Island Rail Road to increase service reliability and improve the customer experience.

East Yaphank Sign
Station

New Yaphank Station

East Yaphank

Design and identification of new station site locations is underway.

Northport Masthead 11-08-18
Completed

Northport Station Enhancement (Completed 01/2019)

Northport

Northport Station has received modernized station enhancements and upgrades.

Completed

Nostrand Ave Station Rehabilitation (Completed 01/2020)

Brooklyn

Nostrand Avenue Station has received modernized station enhancements and upgrades.

Ocean Avenue Substation Prior to Construction
Infrastructure Improvements

Ocean Avenue Substation Replacement

Rockville Centre

The Ocean Avenue substation will be replaced to provide more reliable power to LIRR trains.

Pinelawn Station Enhancement (Completed 09/2018)
Station

Pinelawn Station Enhancement (Completed 09/2018)

Ronkonkoma Branch

Pinelawn Station has been modernized and improved.

Winter 2018 – Plainfield Ave Bridge Prior to Construction
Bridges

Plainfield Avenue Bridge Modification (Completed 04/2020)

Floral Park

Plainfield Avenue Bridge is being modified to reduce truck strikes and improve infrastructure.

Plaza and Entrance - Port Jefferson Station - 01-29-19
Completed

Port Jefferson Station Enhancement (Completed 03/2019)

Port Jefferson

Port Jefferson Station has received modernized station enhancements and upgrades.

Port Washington Substation Replacement (Completed 01/2019)
Completed

Port Washington Substation Replacement (Completed 01/2019)

Port Washington

The Port Washington Substation has been replaced.

Infrastructure Improvements

Positive Train Control

Long Island

Positive Train Control is being integrated into LIRR infrastructure to enhance railroad safety.

Bridges

Post Avenue Bridge Replacement (Completed 10/2017)

Westbury

The successful Post Avenue Bridge replacement serves as a construction model for bridge improvements throughout Long Island.

Rockville Centre Viaduct Rehabilitation
Bridges

Rockville Centre Viaduct Rehabilitation

Rockville Centre

The Rockville Centre Viaduct is being rehabilitated and repaired, including improvements to the existing drainage system.

Ronkonkoma Station 12-12-2018
Completed

Ronkonkoma Station Enhancement (Completed 3/2019)

Ronkonkoma

Ronkonkoma Station has been modernized and improved.

Rosedale Substation Replacement
Infrastructure Improvements

Rosedale Substation Replacement

Rosedale

Rosedale substation will be replaced to provide more reliable power to LIRR trains.

Completed

Sandy Substation Restoration / Long Beach Branch (Completed 01/2018)

Oceanside, Oil City, and Long Beach

Replacement of three substations along the Long Beach Branch has been successfully completed.

School Street Grade Crossing Elimination 11-13-20
Completed

School Street Grade Crossing Elimination (Completed 11/2020)

Westbury

The School Street grade crossing is being eliminated to alleviate train and vehicular traffic and to increase safety.

South 12th Street Grade Crossing Prior to Construction
Grade Crossings

South 12th Street Grade Crossing Elimination

New Hyde Park

Vehicular traffic crossing the LIRR tracks at the South 12th Street grade crossing will be permanently closed and redirected.

Bridges

South Tyson Avenue Bridge Modification (Completed 09/2019)

Floral Park

The South Tyson Avenue Bridge has been replaced to accommodate a new third track.

Springfield Boulevard Bridge 09-25-19
Bridges

Springfield Boulevard Bridge Rehabilitation (Completed 8/2019)

Queens

The rehabilitated Springfield Boulevard Bridge will keep LIRR in a state-of-good-repair.

Stewart Manor Station Enhancement (Completed 01/2019)
Completed

Stewart Manor Station Enhancement (Completed 01/2019)

Garden City

Stewart Manor Station has been modernized and improved.

Stony Brook 11-20-2018
Completed

Stony Brook Station Enhancement (Completed 04/2019)

Stony Brook

Stony Brook Station has received modernized station enhancements and upgrades.

Syosset Station Enhancement (Completed 06/2019)
Completed

Syosset Station Enhancement (Completed 06/2019)

Syosset

Syosset Station has received modernized station enhancements and upgrades.

Tanners Pond / Denton Avenue Bridge Replacement Pre-Construction
Bridges

Tanners Pond / Denton Avenue Bridge Replacement

Garden City

Tanners Pond Road / Denton Avenue Bridge will be replaced to reduce truck strikes and improve infrastructure.

Urban Avenue Grade Crossing Elimination 11-13-19
Completed

Urban Avenue Grade Crossing Elimination (Completed 09/2019)

Town of North Hempstead
Hamlet of New Cassel

Urban Avenue Grade Crossing Elimination – Completed September 2019

Valley Stream Station Enhancement (Completed 02/2019)
Completed

Valley Stream Station Enhancement (Completed 02/2019)

Valley Stream

Valley Stream Station has received modernized station enhancements and upgrades.

Wantagh Station Platform Replacement (Completed 10/2018)
Completed

Wantagh Station Platform Replacement (Completed 10/2018)

Wantagh

The $27 Million renovation project at Wantagh Station is finished.

Webster Avenue Bridge Pre-Construction Phase
Bridges

Webster Avenue Bridge Rehabilitation

Manhasset

The rehabilitation of the aging Webster Avenue Bridge will enhance safety and reduce maintenance on the Port Washington Branch.

Parking

Westbury North Parking Structure

Westbury

A new parking garage is being constructed north of Westbury Station.

Parking

Westbury South Parking and LIRR Lot Development

Westbury

The MTA is working with the Village to accommodate new parking and redevelopment south of Westbury Station.

Westbury Station Enhancement (rendering)
Station

Westbury Station Enhancement

Westbury

Westbury Station will receive modernized station enhancements and upgrades.

Westbury Substation Replacement
Infrastructure Improvements

Westbury Substation Replacement

Westbury

The Westbury substation will be replaced to accommodate the additional third track on the Main Line.

Grade Crossings

Willis Avenue Grade Crossing Elimination

Mineola

The Willis Avenue grade crossing is being eliminated to alleviate train and vehicular congestion and improve safety.

Wreck Lead Bridge 10-31-18
Bridges

Wreck Lead Bridge Rehabilitation

Island Park

The rehabilitation of the aging Wreck Lead Bridge will improve the operational reliability of the bridge.

Completed

Wyandanch Station Enhancement (Completed 09/2018)

Wyandanch

Wyandanch Station has received modernized station enhancements and upgrades.

East End Gateway Entrance 12-31-20
System Expansion

East End Gateway and LIRR Concourse

Manhattan

The 33rd Street Corridor will be widened and redesigned and accessible from a new entrance pavilion.

East Side Access Removed 08-03-2018
System Expansion

East Side Access

Queens, Manhattan

A transformative project connecting LIRR to Grand Central Terminal.

Project Rendering
System Expansion

Jamaica Capacity Improvements

Jamaica, Queens

A comprehensive reconfiguration of Jamaica Station is currently underway to improve capacity and reliability.

Completed

LIRR Double Track Project Farmingdale to Ronkonkoma (Completed 09/2018)

Farmingdale to Ronkonkoma

The Double Track Project introduces 13 miles of a new second track between Farmingdale and Ronkonkoma.

LIRR Expansion Project Floral Park to Hicksville
System Expansion

LIRR Expansion Project Floral Park to Hicksville

Floral Park to Hicksville

The LIRR Expansion Project will introduce 9.8 miles of a new third track, close dangerous grade crossings and upgrade stations along this heavily traversed corridor.

Completed

Mid-Suffolk Train Storage Yard (Completed 11/2020)

Ronkonkoma

An expanded train storage yard and a new employee facility are being built to meet the anticipated increase in AM and PM peak ridership once East Side Access opens in 2022.

Moynihan Train Hall (rendering)
Completed

Moynihan Train Hall (Completed 12/2020)

Manhattan

The new Moynihan Train Hall will alleviate overcrowding at Penn Station and improve the customer experience for LIRR passengers.

New M9 Rail Cars
System Expansion

New M9 Rail Cars

Long Island

The next generation of commuter rail cars is coming to the Long Island Rail Road to increase service reliability and improve the customer experience.

Accabonac Road - 11-18-19
Bridges

Accabonac Road / North Main Street Bridge Replacements (Completed 11/2019)

East Hampton

Accabonac Road and North Main Street bridges have been replaced to reduce truck strikes and improve infrastructure.

Buckram Road Bridge Replacement 02-20-20
Bridges

Buckram Road Bridge Replacement (Completed 10/2019)

Town of Oyster Bay
Hamlet of Locust Valley

Buckram Road Bridge has been replaced to reduce truck strikes and improve infrastructure.

Cherry Lane Bridge 06-03-19
Bridges

Cherry Lane Bridge Replacement (Completed 06/2019)

Town of North Hempstead
Hamlet of Carle Place

Cherry Lane Bridge has been replaced to reduce truck strikes and improve infrastructure.

Cherry Valley Road Bridge Prior to Construction
Bridges

Cherry Valley Road Bridge Replacement

Garden City

Cherry Valley Road Bridge will be replaced to reduce truck strikes and improve infrastructure.

Flushing Main Street Bridge
Bridges

Flushing Main Street Bridge Rehabilitation (Completed 11/2019)

Flushing

Flushing Main Street Bridge has been rehabilitated.

Glen Cove Rd Bridge 09-22-20
Bridges

Glen Cove Road Bridge Replacement (Completed 06/2020)

Town of North Hempstead
Hamlet of Carle Place

Glen Cove Road Bridge is being replaced to improve infrastructure and accommodate a new third track on the mainline.

Lynbrook Viaduct - 10-24-19
Bridges

Lynbrook Viaduct Rehabilitation

Lynbrook

The Lynbrook Viaduct is being rehabilitated and repaired, including improvements to the existing drainage system.

Bridges

Meadowbrook Parkway Bridge Modification (Completed 9/2020)

Town of North Hempstead
Hamlet of Carle Place

Meadowbrook Parkway Bridge is being modified to improve infrastructure and to accommodate a third track on the Main Line.

Nassau Bridge 02-14-20
Bridges

Nassau Boulevard Bridge Replacement (Completed 10/2019)

Garden City

Nassau Boulevard Bridge Replacement – Completed October 2019

Winter 2018 – Plainfield Ave Bridge Prior to Construction
Bridges

Plainfield Avenue Bridge Modification (Completed 04/2020)

Floral Park

Plainfield Avenue Bridge is being modified to reduce truck strikes and improve infrastructure.

Bridges

Post Avenue Bridge Replacement (Completed 10/2017)

Westbury

The successful Post Avenue Bridge replacement serves as a construction model for bridge improvements throughout Long Island.

Rockville Centre Viaduct Rehabilitation
Bridges

Rockville Centre Viaduct Rehabilitation

Rockville Centre

The Rockville Centre Viaduct is being rehabilitated and repaired, including improvements to the existing drainage system.

Bridges

South Tyson Avenue Bridge Modification (Completed 09/2019)

Floral Park

The South Tyson Avenue Bridge has been replaced to accommodate a new third track.

Springfield Boulevard Bridge 09-25-19
Bridges

Springfield Boulevard Bridge Rehabilitation (Completed 8/2019)

Queens

The rehabilitated Springfield Boulevard Bridge will keep LIRR in a state-of-good-repair.

Tanners Pond / Denton Avenue Bridge Replacement Pre-Construction
Bridges

Tanners Pond / Denton Avenue Bridge Replacement

Garden City

Tanners Pond Road / Denton Avenue Bridge will be replaced to reduce truck strikes and improve infrastructure.

Webster Avenue Bridge Pre-Construction Phase
Bridges

Webster Avenue Bridge Rehabilitation

Manhasset

The rehabilitation of the aging Webster Avenue Bridge will enhance safety and reduce maintenance on the Port Washington Branch.

Wreck Lead Bridge 10-31-18
Bridges

Wreck Lead Bridge Rehabilitation

Island Park

The rehabilitation of the aging Wreck Lead Bridge will improve the operational reliability of the bridge.

Parking

Floral Park Parking Re-Surfacing at Creedmoor Spur

Floral Park

This popular Village parking area will be repaved and restriped.

Parking

Hicksville Parking/Downtown Revitalization Initiative

Hicksville

The MTA is working with the Town to fulfill their vision of a walkable community that enlivens the train station area.

Parking

Mineola 2nd Street Parking

Mineola

New parking is planned at the Mineola Station Second Street Parking Lot.

Mineola Harrison Avenue Parking Structure 10-25-19
Parking

Mineola Harrison Avenue Parking Structure

Mineola

A new parking garage is being constructed at Mineola Station west of Mineola Boulevard between Harrison Avenue and First Street.

Parking

Mineola Main Street Parking and Drop-Off

Mineola

New surface parking and a kiss-and-ride will be constructed at Mineola Station.

Parking

New Hyde Park Road Surface Lot

New Hyde Park

A new surface lot and a kiss-and-ride will be constructed at New Hyde Park Station between Plaza Avenue and Second Avenue.

Parking

Westbury North Parking Structure

Westbury

A new parking garage is being constructed north of Westbury Station.

Parking

Westbury South Parking and LIRR Lot Development

Westbury

The MTA is working with the Village to accommodate new parking and redevelopment south of Westbury Station.

Covert Avenue Grade Crossing Elimination Offical Opening of Underpass - 10-17-19
Completed

Covert Avenue Grade Crossing Elimination (Completed 10/2019)

New Hyde Park

Covert Avenue Grade Crossing Elimination – Completed October 2019

Grade Crossings

Main Street Grade Crossing Elimination

Mineola

The elimination of the Main Street grade crossing will alleviate train and vehicular traffic and enhance safety.

Completed

New Hyde Park Road Grade Crossing Elimination (Completed 08/2020)

New Hyde Park

The New Hyde Park Road grade crossing is being eliminated to alleviate train and vehicular traffic and improve safety.

School Street Grade Crossing Elimination 11-13-20
Completed

School Street Grade Crossing Elimination (Completed 11/2020)

Westbury

The School Street grade crossing is being eliminated to alleviate train and vehicular traffic and to increase safety.

South 12th Street Grade Crossing Prior to Construction
Grade Crossings

South 12th Street Grade Crossing Elimination

New Hyde Park

Vehicular traffic crossing the LIRR tracks at the South 12th Street grade crossing will be permanently closed and redirected.

Urban Avenue Grade Crossing Elimination 11-13-19
Completed

Urban Avenue Grade Crossing Elimination (Completed 09/2019)

Town of North Hempstead
Hamlet of New Cassel

Urban Avenue Grade Crossing Elimination – Completed September 2019

Grade Crossings

Willis Avenue Grade Crossing Elimination

Mineola

The Willis Avenue grade crossing is being eliminated to alleviate train and vehicular congestion and improve safety.

Baldwin Station 11-08-18
Completed

Baldwin Station Enhancement (Completed 06/2019)

Baldwin

Baldwin Station has received modernized station enhancements and upgrades.

Bayside Station
Completed

Bayside Station Enhancement (Completed 03/2019)

Bayside

Bayside Station has received modernized station enhancements and upgrades.

Bellmore Station Enhancement (Completed 06/2019)
Completed

Bellmore Station Enhancement (Completed 06/2019)

Bellmore

Bellmore Station has received modernized station enhancements and upgrades.

Brentwood Station 11-08-18
Completed

Brentwood Station Enhancement (Completed 06/2019)

Brentwood

Brentwood Station has received modernized station enhancements and upgrades.

Carle Place Station Enhancement (rendering)
Station

Carle Place Station Enhancement

Town of North Hempstead
Hamlet of Carle Place

Carle Place Station is receiving modernized station enhancements and upgrades.

Deer Park Dahlias (2018) © William Low, LIRR Deer Park Station
Completed

Deer Park Station Enhancement (Completed 04/2019)

Baywood

Deer Park has received modernized station enhancements and upgrades.

Completed

East Hampton Station Enhancement (Completed 04/2019)

East Hampton

East Hampton has received modernized station enhancements and upgrades

Station

Elmont Station

Elmont

The new Elmont LIRR Station, the first new full-time LIRR station in nearly 50 years, is part of the $1.26 billion Belmont Park Redevelopment Project.

Farmingdale Station 11-08-18
Completed

Farmingdale Station Enhancement (Completed 04/2019)

Farmingdale

Farmingdale Station has received modernized station enhancements and upgrades.

Floral Park Station - 03-07-19
Station

Floral Park Station Enhancement

Floral Park

Floral Park Station is receiving modernized station enhancements and upgrades.

Flushing Main Street Station 8-31-2018
Station

Flushing Main Street Station Enhancement (Completed 08/2018)

Flushing, Queens

Flushing Main Street Station has received modernized station enhancements and upgrades.

Completed

Great Neck Station Enhancement (Completed 04/2019)

Great Neck

Great Neck Station has received modernized station enhancements and upgrades.

Hempstead Station - 03-12-19
Completed

Hempstead Station Enhancement (Completed 07/2019)

Hempstead Station

Hempstead Station has received modernized station enhancements and upgrades.

Hicksville Station Improvements Project (Completed 08/2018)
Completed

Hicksville Station Improvements Project (Completed 08/2018)

Hicksville

Hicksville Station has been completely renovated with modernized station enhancements and upgrades.

Laurelton Station - 03-12-19
Completed

Laurelton Station Enhancement (Completed 12/2019)

Laurelton

Laurelton Station has been improved and modernized.

Locust Manor Station Enhancement - 03-12-19
Completed

Locust Manor Station Enhancement (Completed 05/2019)

Locust Manor

Locust Manor Station has been modernized and upgraded.

Lynbrook Station Enhancement (rendering)
Completed

Lynbrook Station Enhancement (Completed 10/2020)

Lynbrook

The Lynbrook Station infrastructure is being renewed and its amenities are being upgraded.

Station

Merillon Avenue Station Enhancement

Garden City

Merillon Station will receive modernized station enhancements and upgrades.

Merrick Station Enhancement
Completed

Merrick Station Enhancement (Completed 01/2019)

Merrick

Merrick Station has received modernized station enhancements and upgrades.

Mets-Willets Point Station Pre-Construction
Station

Mets-Willets Point Station

Flushing, Queens

The seasonal Mets-Willets Point Station will receive modernized station enhancements and upgrades.

Station

Mineola Station Enhancement

Mineola

Mineola Station will receive modernized station enhancements and upgrades.

Murray Hill Station prior to enhancements
Completed

Murray Hill Station – New Elevators (Completed 04/2020)

Queens

Murray Hill Station is receiving modernized station enhancements and upgrades.

Station

New Hyde Park Station Enhancement

New Hyde Park

New Hyde Park Station will receive modernized station enhancements and upgrades.

East Yaphank Sign
Station

New Yaphank Station

East Yaphank

Design and identification of new station site locations is underway.

Northport Masthead 11-08-18
Completed

Northport Station Enhancement (Completed 01/2019)

Northport

Northport Station has received modernized station enhancements and upgrades.

Completed

Nostrand Ave Station Rehabilitation (Completed 01/2020)

Brooklyn

Nostrand Avenue Station has received modernized station enhancements and upgrades.

Pinelawn Station Enhancement (Completed 09/2018)
Station

Pinelawn Station Enhancement (Completed 09/2018)

Ronkonkoma Branch

Pinelawn Station has been modernized and improved.

Plaza and Entrance - Port Jefferson Station - 01-29-19
Completed

Port Jefferson Station Enhancement (Completed 03/2019)

Port Jefferson

Port Jefferson Station has received modernized station enhancements and upgrades.

Ronkonkoma Station 12-12-2018
Completed

Ronkonkoma Station Enhancement (Completed 3/2019)

Ronkonkoma

Ronkonkoma Station has been modernized and improved.

Stewart Manor Station Enhancement (Completed 01/2019)
Completed

Stewart Manor Station Enhancement (Completed 01/2019)

Garden City

Stewart Manor Station has been modernized and improved.

Stony Brook 11-20-2018
Completed

Stony Brook Station Enhancement (Completed 04/2019)

Stony Brook

Stony Brook Station has received modernized station enhancements and upgrades.

Syosset Station Enhancement (Completed 06/2019)
Completed

Syosset Station Enhancement (Completed 06/2019)

Syosset

Syosset Station has received modernized station enhancements and upgrades.

Valley Stream Station Enhancement (Completed 02/2019)
Completed

Valley Stream Station Enhancement (Completed 02/2019)

Valley Stream

Valley Stream Station has received modernized station enhancements and upgrades.

Wantagh Station Platform Replacement (Completed 10/2018)
Completed

Wantagh Station Platform Replacement (Completed 10/2018)

Wantagh

The $27 Million renovation project at Wantagh Station is finished.

Westbury Station Enhancement (rendering)
Station

Westbury Station Enhancement

Westbury

Westbury Station will receive modernized station enhancements and upgrades.

Completed

Wyandanch Station Enhancement (Completed 09/2018)

Wyandanch

Wyandanch Station has received modernized station enhancements and upgrades.

Bellmore Substation 2-13-18
Infrastructure Improvements

Bellmore Substation Replacement

Bellmore

The Bellmore substation will be replaced to provide more reliable power to LIRR trains.

Carle Place Substation
Infrastructure Improvements

Carle Place Substation Replacement

Carle Place

The Carle Place substation will be replaced to accommodate the additional third track on the Main Line.

Infrastructure Improvements

Floral Park Substation Modifications

Floral Park

The Floral Park substation will be modified to accommodate the additional third track on the Main Line.

Infrastructure Improvements

Hicksville Substation Replacement

Hicksville

The Hicksville substation will be replaced to accommodate the additional third track on the Main Line.

Linden Avenue Pedestrian Underpass 04-29-20
Completed

Linden Avenue Pedestrian Underpass (Completed 04/2020)

Village of Floral Park

The pedestrian underpass at Linden Avenue in Floral Park is being replaced to accommodate the new third track on the Main Line.

Meadowbrook Substation Replacement 10-12-18
Completed

Meadowbrook Substation Replacement (Completed 06/2020)

Freeport

The Meadowbrook substation will be replaced to provide more reliable power to LIRR trains.

Infrastructure Improvements

Merillon Avenue Substation Replacement

Garden City

The Mineola substation, located at the southwest corner of Main Street and Front Street in Mineola, will be replaced as part of the LIRR Expansion Project.

Mineola Substation Prior to Construction
Infrastructure Improvements

Mineola Substation Replacement

Mineola

The Mineola substation, located at the southwest corner of Main Street and Front Street in Mineola, will be replaced as part of the LIRR Expansion Project from Floral Park to Hicksville.

Completed

Morris Park Diesel Locomotive Shop (Completed 11/2020)

Queens

Morris Park Diesel Locomotive Shop is receiving upgrades to maximize efficiency.

Murray Hill Substation – 01-29-19
Infrastructure Improvements

Murray Hill Substation Replacement

Queens

The Murray Hill substation will be replaced to provide more reliable power to LIRR trains.

Infrastructure Improvements

New Cassel Substation Replacement

New Cassel

The New Cassel substation will be replaced to accommodate the additional third track on the Main Line.

New Hyde Park Substation Replacement
Infrastructure Improvements

New Hyde Park Substation Replacement

New Hyde Park

The New Hyde Park substation will be replaced to accommodate the additional third track on the Main Line.

Ocean Avenue Substation Prior to Construction
Infrastructure Improvements

Ocean Avenue Substation Replacement

Rockville Centre

The Ocean Avenue substation will be replaced to provide more reliable power to LIRR trains.

Port Washington Substation Replacement (Completed 01/2019)
Completed

Port Washington Substation Replacement (Completed 01/2019)

Port Washington

The Port Washington Substation has been replaced.

Infrastructure Improvements

Positive Train Control

Long Island

Positive Train Control is being integrated into LIRR infrastructure to enhance railroad safety.

Rosedale Substation Replacement
Infrastructure Improvements

Rosedale Substation Replacement

Rosedale

Rosedale substation will be replaced to provide more reliable power to LIRR trains.

Completed

Sandy Substation Restoration / Long Beach Branch (Completed 01/2018)

Oceanside, Oil City, and Long Beach

Replacement of three substations along the Long Beach Branch has been successfully completed.

Westbury Substation Replacement
Infrastructure Improvements

Westbury Substation Replacement

Westbury

The Westbury substation will be replaced to accommodate the additional third track on the Main Line.