The Carle Place substation, located at the southeast quadrant of Meadowbrook State Parkway and the LIRR just north of Mallard Road, will be replaced as part of the LIRR Expansion Project from Floral Park to Hicksville. This substation is approximately 40 years old and nearing the end of its operational life. The Carle Place substation replacement is a key component in accommodating the additional third track and supporting future growth of the LIRR. The Carle Place substation replacement is part of a larger initiative to enhance service reliability and support system expansion throughout the LIRR and ultimately support the growth and development of Long Island.
On January 16th, Third Track Constructors (3TC), the Design-Build contractor for the LIRR Expansion Project, presented a project update to the Garden City Public Schools Board of Education and discussed how the team is managing ongoing coordination with local schools.
On January 15th, Mayor Peter Cavallaro of Westbury hosted a productive dialogue for the LIRR Expansion Project team with Town of North Hempstead Supervisor Judi Bosworth, Councilwoman Viviana Russell, residents of the Village of Westbury and residents of the Hamlet
Construction of the LIRR Expansion Project from Floral Park to Hicksville is well underway. As part of this Project, MTACC/LIRR have developed a series of environmental and community commitments in coordination with Project-adjacent communities to minimize construction-related impacts. MTACC/LIRR have
On January 11th, LIRR Expansion Project Team members met with State Senator Anna Kaplan and officials from the Town of North Hempstead, including Town Supervisor Judi Bosworth and Councilwoman Viviana Russell, to discuss various Expansion Project components within North Hempstead.
Field Engineer Greg Kelty of 3rd Track Constructors, the project Design-Build contractor, has procured samples of sound and retaining walls for the LIRR Expansion Project. The LIRR Expansion Project includes the installation of several types of retaining and sound attenuation
A commuter rail system in the US state of New York, Long Island Rail Road (LIRR), has replaced the Port Washington electrical substation to boost the reliability of railway services.
On January 3, 2018, Long Island Rail Road President Phillip Eng announced the LIRR had completed work to replace the Port Washington electrical substation, on time and on budget. The new substation, which was built at a cost of $26.2
LIRR President Phil Eng and members of the LIRR Expansion Project team were honored to welcome incoming State Senator Anna Kaplan to the LIRR Expansion Project Community Information Center in Mineola. The briefing included an overview of the project, a
On December 20, 2018, community leaders and Nassau County officials from LIRR Expansion Project-adjacent villages and towns gathered for a monthly project update presentation and discussion at the new Community Information Center in Mineola. The Community Information Center is located
The December construction look-aheads for the LIRR Expansion Project have been posted. These look-aheads are part of the Expansion Project team’s commitment to communicate with residents of communities along the project, on all aspects of the project, to keep them